Progress Update on the 21st Hive Borehole Project.
Today, an update on the construction progress of the 21st Hive Borehole, now underway in Ghana! And let me just say this particular venture will see us mark a major milestone, closing out our powerful twentieth chapter before pausing to take stock of where we stand so far. It’s good as construction gets off the ground, and now we have entered Phase 2.
The main pillar to hold up the tank and stand-in structure is erected successfully. This is a vital step, for it lays groundwork which ensures that a steady flow of water will reach communities via their infrastructured facilities. As always, the highly skilled workers on site have shown their commitment and efficiency in executing this part of the project both quickly and safely.
Phase 3 is already underway; this involves connecting plumbing and laying the groundwork for tank and pump stations. The team has moved quickly and accurately so far to make sure that everything lives up to the high standards of quality set by Hive development projects over all these years. With the current pace of work and foreseeing a smooth flow right up until its completion, we hope to finish our borehole by early next week.
This provides us with an ideal schedule, for we can then plan an exciting inauguration ceremony next Saturday, which will mark yet another community obtaining clean, renewable freshwater. This is more than just infrastructure—it represents progress via the power of blockchain and Hive. And the vibration of every single borehole really hits far beyond the infrastructure completion date, as they positively transform lives every day in communities around Ghana's villages or towns.
Please watch for new updates and more photos as we near the end of construction of this 21st borehole. Take the time right now to forward this on, giving encouragement and showing people that with technology there are no limits to what can be done when you bring it together in service of human need.
Completed Hive Boreholes in Ghana
1st hive borehole, Fawoade, Ghana
2nd hive borehole, Agona Bedomase, Ghana
3rd hive borehole, Anwomaso, Ghana
4th hive borehole: Pentecost sch Bremang, Ghana
5th hive borehole, Jamasi Dawu
11th hive borehole, Kanvili-kukuo
12th hive borehole, Asamankama A
13th hive borehole: Asamankama B
14th hive borehole: Wadie Adwumakase
15th hive borehole: Nantong Kpawumo
17th hive borehole : Nsuta Kwagyei
20th hive borehole : Bampenase
Project : Construction of borehole
Location : Asomanya, Ghana, West Africa
Sponsor : @valueplan
Project manager : @mcsamm & @collinz
Changing lives with hive.
I love seeing this. It keeps me motivated and to believe in the blockchain the more.
Best regards.
!BBH
Great progress.
The work is massively under way and going very fast.
It’s great so find such passion for your people..posterity will always remember all of these. More territories to bless
Weldone boss
Thanks buddy.
I’m so excited about this and the fact that they are already near the end? That’s amazing news
21 boreholes is such a huge milestone. Shout out to you and your team.